Incident: Power Short Circuit — PCB v1

Date: 2026-03-26 Severity: Critical (board non-functional) Affected boards: 5/5 (100%) — design bug, not component failure Status: Root cause identified, fix applied in routing.py, boards reworkable Update 2026-03-28: BUG #3 discovered (LCD_RST bridge), full 44-violation map completed

Symptoms

Six power decoupling capacitors measured 0 ohm (short to GND) on all 5 assembled boards:

#RefPosition (mm)PackageNet (pad+)Net (pad-)ExpectedMeasured
1C17(110, 35.0)0805VBUSGND>1M ohm~0 ohm
2C1(122, 48.5)0805+5VGND>1M ohm~0 ohm
3C18(118, 55.0)0805BAT+GND>1M ohm~0 ohm
4C19(110, 58.5)1206+5VGND>1M ohm~0 ohm
5C2(125, 62.5)1206+3V3GND>1M ohm~0 ohm
6C3(69.5, 42.0)0805+3V3GND>1M ohm~0 ohm

USB-C connector (J1) was desoldered — short persisted, ruling out connector as cause.

Root Cause: Via-to-Trace Overlap on F.Cu

Two vias from capacitor C19 overlapped the VBUS power trace on the front copper layer (F.Cu), creating a direct metallurgical short that chained all power rails to GND.

Bug #1: GND via overlaps VBUS horizontal trace

          VBUS horizontal trace (F.Cu, width=0.5mm)
y=61.25 ─────────────────────────────────────── top edge
y=61.00 ═══════════════════════════════════════ centerline
y=60.75 ─────────────────────────────────────── bottom edge
y=60.95 ·····o····· GND via annular ring top <-- OVERLAP 0.20mm
y=60.50 (*) GND via center
y=60.05 ·····o····· GND via annular ring bottom

x=82 x=108.5 x=111

The GND via annular ring (r=0.45mm) extended to y=60.95, but the VBUS trace bottom edge was at y=60.75. 0.20mm copper overlap = direct short.

Bug #2: +5V via overlaps VBUS vertical trace

        VBUS vertical trace (F.Cu, width=0.5mm)
x=110.75 | | x=111.25
| |
x=111.05 |.....|.o +5V via annular ring left <-- OVERLAP 0.20mm
| |(*) +5V via center @x=111.50
x=111.95 | | o +5V via annular ring right

Short Propagation Chain

The two F.Cu violations created a chain that shorted ALL power rails to GND:

                F.Cu Layer Violations
=====================

GND via ──────── overlaps ──────── VBUS trace
@(108.5, 60.5) -0.20mm @y=61.0
| |
| | same trace
| |
| +5V via ──── overlaps ──── VBUS trace
| @(111.5, 56.5) -0.20mm @x=111.0
| |
v v
GND ====== VBUS ====== +5V
|
AMS1117 (U3)
|
+3V3

Result: Every power rail reads 0 ohm to GND through F.Cu copper overlap.

F.Cu Routing — Problem Area Diagram

F.Cu Layer (front copper) — power trace routing

y=40 --- - - - - - - - - - - - - - - - - - - - -
# VBUS vertical @x=111
# (width 0.5mm)
y=48 --- - - - - - - - -#- - - - - - - - - - - -
#
#
y=56 --- - - - - - - - -#- - - - - - - - - - - -
o#<-- BUG #2: +5V via @(111.5, 56.5)
# overlaps VBUS vert (-0.20mm)
#
y=60 --- - - - - - - - -#- - - - - - - - - - - -
o #
^ #
y=61 =======X==========X=== VBUS horizontal @y=61
| # (width 0.5mm, x=82->111)
| #
BUG #1: GND via #
@(108.5, 60.5) #
overlaps VBUS #
horiz (-0.20mm) #
#
x=82 x=108.5 x=111

Legend: === VBUS trace o via (wrong clearance)

Component Map (B.Cu Bottom Layer)

B.Cu viewed from back (X mirrored) — as seen in photos
Board: 160 x 75 mm

+-------------------------------------------------------------+
| [btn L] [btn R] |
| |
| [FPC J4] [ESP32-S3 U1] [PAM8403 U4] |
| || || +--------------+ +--------+ |
| || || !C17 | | | | |
| || || (110,35)| (80,27.5) | |(30,30) | |
| * | | | | |
| U2 IP5306 +--------------+ +--------+ |
| !C1 (110,42.5) |
| (122,49) !C3 |
| ##L1## (69.5,42) |
| !C18 (110,52.5) |
| (118,55) U3 AMS1117 |
| (125,55.5) R4 R5 R6 ..... R14 R15 R19 |
| !C19 C5 C6 C7 ..... C15 C16 C20 |
| !C2 (110,58.5) |
| (125,63) |
| |
| [btn] [SD] [JST bat] [USB-C] [btn] [switch] |
+-------------------------------------------------------------+

! = shorted capacitor * = IP5306 (NOT the culprit)

Origin of the Bug

Both problematic vias were generated by C19 (1206 capacitor, +5V/GND, at 110, 58.5 on B.Cu):

# routing.py — C19 via generation (BEFORE fix)
# C19 pad "1" (+5V) at (111.5, 58.5) -> via at (111.5, 56.5) <-- BUG #2
# C19 pad "2" (GND) at (108.5, 58.5) -> via at (108.5, 60.5) <-- BUG #1

C19 was added during a DFM fix that moved it to (110, 58.5), but its via offsets (+-2mm vertical) were never checked against the VBUS F.Cu traces at y=61 and x=111. The VBUS route had been changed to y=61 in "SHORT FIX v4" — placing it exactly in the path of C19's vias.

Why It Wasn't Caught

CheckWhy it missed
Collision grid (routing.py)Reported 186 violations total, but power shorts were buried among 180+ FPC/display violations. Not treated as blocking errors.
verify_dfm_v2.pyChecks pad spacing, drill sizes, silk clearance — does NOT check via-to-trace clearance
verify_dfa.pyChecks assembly (rotation, BOM, CPL) — not copper routing
KiCad DRCZone fill might mask the overlap if GND zone creates thermal relief
JLCPCB review0.2mm overlap below typical visual inspection threshold
Visual inspectionF.Cu side is under the display — not visible during testing

Fix Applied (routing.py)

Fix 1: GND via — reduce Y offset

# BEFORE: via at y = pad_y + 2.0 = 60.5 (overlaps VBUS @y=61)
# AFTER: via at y = pad_y + 1.0 = 59.5 (gap = 0.80mm)
parts.append(_seg(c19_p2[0], c19_p2[1], c19_p2[0], c19_p2[1] + 1.0,
"B.Cu", W_SIG, n_gnd))
parts.append(_via_net(c19_p2[0], c19_p2[1] + 1.0, n_gnd))

Fix 2: +5V via — route horizontally to clear VBUS vertical

# BEFORE: via at (111.5, 56.5) — overlaps VBUS vert @x=111
# AFTER: route B.Cu horizontal to x=113, then via at (113, 56.5)
# gap to VBUS: 113 - 0.45 - 111.25 = 1.30mm
safe_x = 113.0
parts.append(_seg(c19_p1[0], c19_p1[1], safe_x, c19_p1[1],
"B.Cu", W_SIG, NET_ID["+5V"]))
parts.append(_seg(safe_x, c19_p1[1], safe_x, c19_p1[1] - 2,
"B.Cu", W_SIG, NET_ID["+5V"]))
parts.append(_via_net(safe_x, c19_p1[1] - 2, NET_ID["+5V"]))

Clearance verification after fix

ViaOld positionNew positionGap to VBUSStatus
GND(108.5, 60.5)(108.5, 59.5)0.80mmPASS
+5V(111.5, 56.5)(113.0, 56.5)1.30mmPASS

All 114 DFM tests and 9 DFA assembly tests pass after regeneration.

Rework Procedure for Existing Boards

The fix is surgical but simple: scrape copper on F.Cu to create clearance around 2 vias. No jumper wires needed — vias still connect to GND (In1.Cu) and +5V (In2.Cu) through inner power planes.

Tools needed

  • Precision knife (X-Acto) or scalpel
  • Magnifying glass or loupe (10x)
  • Multimeter (continuity mode)
  • Isopropyl alcohol + cotton swab
  • Optional: clear nail polish or UV solder mask for protection

Step-by-step

Preparation

  1. Remove display panel (unclip FPC ribbon)
  2. Clean F.Cu (top/display) side with isopropyl alcohol
  3. Locate the 2 vias on F.Cu:
F.Cu (top/display side) — looking down at the board

VBUS vertical trace
@x=111, width 0.5mm
|#|
|#|
+5V via ----------> --|o|-- y=56.5
(111.5, 56.5) |#| Scrape HERE: isolate via ring
r=0.45mm |#| from VBUS trace on LEFT side
|#|
|#|
|#|
======================X#X======== VBUS horizontal @y=61
---|o|--- width 0.5mm
| |
GND via ------------> (108.5, 60.5)
r=0.45mm Scrape HERE: isolate via ring
from VBUS trace ABOVE

Via 1: GND via at (108.5, 60.5) — overlaps VBUS horizontal

  1. Find the GND via on F.Cu — ~2.5mm LEFT of the corner where VBUS horizontal meets vertical
  2. With a scalpel blade, scrape a thin line (0.3mm) of copper between:
    • The TOP edge of the via ring (y ~ 60.95)
    • The BOTTOM edge of the VBUS horizontal trace (y ~ 60.75)
  3. Cut direction: horizontal, parallel to the VBUS trace
  4. Verify with multimeter: via pad vs VBUS trace = open circuit

Via 2: +5V via at (111.5, 56.5) — overlaps VBUS vertical

  1. Find the +5V via — ~4.5mm ABOVE Via 1, ~3mm to the RIGHT
  2. Scrape a thin line (0.3mm) of copper between:
    • The LEFT edge of the via ring (x ~ 111.05)
    • The RIGHT edge of the VBUS vertical trace (x ~ 111.25)
  3. Cut direction: vertical, parallel to the VBUS trace
  4. Verify with multimeter: via pad vs VBUS trace = open circuit

Cross-section diagram

BEFORE (shorted):

F.Cu ===VBUS===*GND=== <-- via ring touches trace
In1.Cu --------GND------ <-- GND zone
In2.Cu --------+5V------ <-- +5V zone
B.Cu ====C19=pad=*====== <-- C19 GND pad

AFTER (fixed):

F.Cu ===VBUS==X...*GND.. <-- scraped gap, via ring isolated
In1.Cu --------GND------ <-- GND zone still connected to via
In2.Cu --------+5V------ <-- +5V zone still connected
B.Cu ====C19=pad=*====== <-- C19 still works through inner layers

X = scraped copper gap (0.3mm)
* = via (still connects to inner layers through barrel)

Verification

  1. Test ALL 6 capacitors — each should read high impedance (>100k ohm):
#RefExpected after fix
1C17>100k ohm (was 0 ohm)
2C1>100k ohm (was 0 ohm)
3C18>100k ohm (was 0 ohm)
4C19>100k ohm (was 0 ohm)
5C2>100k ohm (was 0 ohm)
6C3>100k ohm (was 0 ohm)

Power-on test

  1. Connect USB-C to a current-limited supply (100mA max, 5V)
  2. Expected: current draw < 50mA (idle, no battery)
  3. If current immediately hits limit — additional short exists, do NOT continue
  4. Measure voltages:
Test pointExpected
VBUS (C17 pad+)5.0V
+5V (C1 pad+)4.8-5.2V
+3V3 (C2 pad+)3.3V
BAT+ (C18 pad+)0V (no battery)

Protection

  1. Apply UV solder mask or clear nail polish over scraped areas
  2. Reattach display panel

Estimated time per board: ~10 minutes

BUG #3: LCD_RST Bridges VBUS and GND (discovered 2026-03-28)

After physically fixing BUG #1 and #2, boards still showed a VBUS-to-GND short. A deeper analysis revealed a third short that was listed in the original collision report (items #9 and #10 in the "Power vs Signal" category) but not recognized as a power bridge.

Root cause

A 40mm-long LCD_RST trace on F.Cu at y=33.0 passes over two different power vias:

ViaNetPositionOverlap
ESP32 GND viaGND(81.50, 32.96)-0.475mm
C17 VBUS viaVBUS(110.95, 33.00)-0.515mm
F.Cu layer — y = 33mm (under display area)

x=79.4 CUT x=95 x=110.95 x=119.6
====o==============================X=============o================
GND via scrape here VBUS via
(81.50, 32.96) (110.95, 33.00)

GND <---- LCD_RST copper ----> VBUS = DIRECT BRIDGE

Why it was missed

The original analysis (section 12.B) listed these as two separate "Power vs Signal" violations. The pairwise check found LCD_RST overlapping a VBUS via and LCD_RST overlapping a GND via independently, but did not recognize that together they formed a power-to-power bridge through the shared signal copper.

Rework

On F.Cu (front/display side), cut the LCD_RST trace at x=95, y=33 (center of board). LCD_RST still functions via B.Cu routing to the FPC connector.

DFM test added

test_power_bridge_detection() now groups violations by trace and flags when a single trace touches vias from 2+ different power nets.

Complete Violation Map (44 total)

Full analysis of all 44 routing violations found on the manufactured PCB (commit adc073b), including 8 power bridges, 19 single-net shorts, and rework procedures for each:

Complete Short Circuit Map and Rework Guide

Summary

SeverityCountDescription
CRITICAL3Power-to-power bridges (BUG #1, #2, #3)
HIGH5+3V3-to-GND bridges via button/USB signal traces
MEDIUM19Signal stuck to single power net
MARGINAL11Gap 0-0.05mm, may not manifest
Total44

Assessment

After fixing BUGs #1-3, power rails should work. However, with 24 additional signal-to-power shorts, the board has limited functionality: display, SD card, several buttons, and USB data lines are affected. A new PCB revision with corrected routing is needed for full functionality.

New DFM Tests Added (2026-03-28)

Four tests added to verify_dfm_v2.py to prevent recurrence:

TestWhat it catchesOld PCB violations
test_via_annular_ring_trace_clearanceVia copper (not just drill) overlapping traces72
test_signal_power_via_overlapSignal trace touching any power via32
test_trace_crossing_same_layerPerpendicular trace crossings55
test_power_bridge_detectionSignal trace bridging 2+ power nets6

Root cause of test gap: test_drill_trace_clearance (test 42) used drill radius (0.175mm) instead of annular ring copper radius (0.45mm) — a 0.275mm blind spot per via.

Lessons Learned

  1. Via placement must be checked against power traces — the collision grid reported this, but violations were not treated as blocking errors
  2. Power-net overlaps must be fatal — any cross-net overlap with gap < 0mm should fail the build
  3. Late component moves need clearance re-verification — C19 was moved during a DFM fix without rechecking its via paths against existing F.Cu routes
  4. Separate power violations from signal violations — 2 critical power shorts were hidden among 180+ signal violations in the collision report
  5. Bridge detection requires grouping, not just pairwise checks — two "signal vs power" violations on the same trace form a power bridge (BUG #3)
  6. Test the right dimension — drill radius != copper radius; the annular ring extends 0.275mm beyond the drill edge